- Result
- No-go Crane pick, level 40 steel, A-2140
- Rule that fired
- Wind gust at or above 25 mph, critical
- Rules as they stood
- Crane Operations, version 3Copied at 7:30. Approved by Dana Whitfield, 3 Aug 2026
- Observed
- Gust 34 mph, sustained 19 mphTomorrow.io, grid point 0.4 mi from site, observed not forecast, retrieved 7:29:41
- Told
- 17 people at 7:30 AMSeen by Josh Rivera, superintendent, 7:34 AM
- Override
- None
The file the contract asks for.
Anyone can keep a weather log. A delay claim, a federal schedule review and an inspector each ask for something more specific, and they say what in public documents. AllClear builds its record to those documents.
A weather-delay claim has three tests. The file answers each one.
Was it abnormal?
Each site is baselined against NOAA's 30-year monthly normals: how many adverse-weather days the month should have had, and how many it did.
UFGS 01 32 17.00 20 sets this baseline.
Did it hit scheduled work?
Every lost day names the activity it stopped, by your own schedule's activity ID and name, with the cause as it was recorded at the time.
AIA A201-2017 §15.1.6.2 asks for an “adverse effect on the scheduled construction”.
Was it material?
A lost day means the crew could not work at least half of it on that activity. You can set a different test per contract. A no-go alone never counts, and a go alone proves nothing: a person confirms what happened.
UFGS 01 32 17.00 20: at least 50 percent of the day on the impacted activity.
Nobody prepares this file. It is the month's daily logs, added up.
Each lost day rests on the superintendent's own answer in that day's log: whether the work stopped, and when it could restart. The specification also asks for a narrative of cause. AllClear does not write one. It supplies the recorded calls and the superintendent's own words to whoever does.
How Daily Log worksAIA Document A201-2017 is the General Conditions of the Contract for Construction, sold by the AIA.
Weather-day file, September 2026
1. Abnormal for the period against NOAA 30-year monthly normals
2. Scheduled activities hit by your own activity ID
| Date | Activity | Lost | Cause, as recorded |
|---|---|---|---|
| Thu 3 Sep | A-1975 Slab pour, level 2 deck | 6.5 of 10 h | Rain, 0.62 in by noon |
| Sat 19 Sep | A-2140 Crane pick, level 40 steel | 8.0 of 10 h | Lightning stand-down 7:13 to 8:11. Gusts at or above 25 mph, 7:30 to 3:30 PM |
| Tue 22 Sep | A-2140 Crane pick, level 40 steel | 10 of 10 h | Gusts at or above 25 mph all shift, peak 41 |
3. Sat 19 Sep, as recorded from that day's log
- 7:12
- Reading supplied:
Thunder heard
, Josh Rivera - 7:13
- No-go, whole site. Lightning rule, Crane Operations version 3
- 7:30
- No-go, A-2140. Gust 34 mph, critical limit 25. 17 told, 17 acknowledged
- 8:11
- Stand-down ended. A-2140 still no-go, gust 31 mph
- 3:30 PM
- End of shift. A-2140 still no-go, gust 27 mph, peak 36
“Wind never came back under 25. Pick moved to Monday.”
8.0 of 10 scheduled hours, 80 percent. Claim notice under the contract is due by 10 Oct 2026, 21 days after the event.
Every call keeps the rule as it stood that morning.
Rules are versioned, with a named approver and the dates each version was in force. A decision copies the limits at the moment it is made, so editing a rule in October cannot change what September's record says.
An override is allowed. It carries a name and a reason, and it sits in the record beside the call it overrode.
Exterior hoist runs
Sustained wind is above the warning limit.
Wind is 17 mph against a 15 mph warning limit in Crane Operations, version 3.
“Continuing hoist runs with a spotter at the landing. Loads under half capacity until wind drops below 15.”
On a hot day, an inspector asks how you monitored the temperature.
OSHA's heat emphasis program took effect on April 10, 2026. It sends inspectors out on any day the National Weather Service issues a heat warning or advisory. Near the top of their question list is how the employer monitored ambient temperature at the worksite, and they note any heat alerts from the days before.
AllClear answers from what it already kept: a reading every 30 minutes, the alerts in effect that day and the days before, the rule your company had adopted, and who was told.
There is no federal heat standard today, and AllClear does not claim to make anyone compliant with anything. It shows what you monitored and what you did.
- How temperature was monitored
- Heat index computed from temperature and humidity every 30 minutes, 6:00 AM to 6:00 PM24 checks that day. Tomorrow.io, grid point 0.7 mi from site
- Alerts in effect
- NWS Heat Advisory, 11 to 13 AugCaptured daily, including the day before
- Rule in force
- Apex Heat Plan, version 2Rest breaks adopted from Oregon OSHA, OAR 437-002-0156 Table 2, as company policy
- What it triggered
- Heat index 96 at 1:30 PM: 20 minutes rest every hour23 people told by text at 1:31 PM. 21 replied OK
Built to line up with NOAA, not to compete with it.
The certified weather record is NOAA's. Certified copies come from NCEI, and most orders start at $191. What NOAA cannot show is what your company knew, when, what its own rule said that day, who was told and who saw it. AllClear keeps that, and tags every reading with its station or grid point, its provider, and whether it was forecast or observed, so the two records can be laid side by side.